Will Your Road be Improved This Summer?

Ledyard Public Works plans to be work on the following roads during the next two summers.

 

Director of Public Works Steve Masalin said this season in road projects will be very busy this year and a little less busy next summer. Below is a list of roads on his "to do" list for the next two seasons, which begin mid-April. The estimated cost of the projects is around $3.2 million.

Masalin rates each road by a variety of factors and said that the Town's present road conditions average out to be a 78 (on a scale from 0-100, with 100 being the highest) and he hopes to bring that up to 80 when the projects are complete.

Find out what's happening in Ledyardwith free, real-time updates from Patch.

Masalin said roads deteriorate according to a standard curve, so deterioration is always happening, even if it is not evident. He takes a proactive approach to maintaining roads in order to get the most out of the money available. To this end, he'll be introducing a new process this year—microsurfacing.

Mill/Overlay (2013)

Find out what's happening in Ledyardwith free, real-time updates from Patch.

Avery Hill Rd

Shewville Rd (Gallup Hill Rd to RT 214)

Whitford Rd

Windward Ln

Overlay (2013)

Aljen Ave

Arrowhead Dr

Barn Rd

Green Point Ct

Hillcrest Ave

Jean B Ct

Johnnie Ct

Laurel Ave

Louis Ave

Michael Ln

Royal Oaks Dr

Sunset Ave

Tucker’s Run

Willow Ln

Microsurfacing (2013, includes touch-up Crack-Sealing)

Gallup Hill Rd (Flintlock Rd to Shewville Rd)

Long Cove Rd

Meetinghouse Ln (Pennywise Ln to Town Farm Rd)

Mathewson Mill Rd

Pumpkin Hill Rd (Lambtown Rd to Groton Town Line)

Spicer Hill Rd (RT 117 to RT 214)

Wendell Comrie Rd

Whalehead Rd (RT 214 to Merry Ln)

Crack-Sealing (2014)

Applewood Dr

August Meadows

Avebury Berwick

Baldwin Hill Rd

Brentford Berwick

Capt Amos Stanton Dr

Chatham Berwick

Haley Rd

Lucienne Way

Marlene Dr

Naomi Dr

Philip Ln

Reservoir View

Rosemarie Ct

Sherwood Trace

Shewville Rd (RT 14 to Preston Town Line)

Town Farm Rd

Outside-Funded Projects

These projects are dependent upon approval of funding through parties outside the Town of Ledyard.  These projects will proceed only when such funding is appropriated through the outside agencies (in this case MPTN through the BIA).

Coachman Pike

Heath Spur

Spout Run

Wicklow Turn

Lantern Hill Rd

White Pine Rd

According to Masalin, "the actual scope and nature of work will be verified for each road at the point of final planning and the overall scope of work of the program is subject to adjustment according to the actual costs encountered and listed projects may be deferred and additional projects may be added."